Customer: BHP Billiton Mitsubishi Alliance

Completion Date: 30/04/2012

Location: BMA Coal Goonyella Riverside Mine

Specifications & Features:

Dowden's have installed and commissioned a new potable water treatment plant at the BMA Goonyella Riverside coal mine

Water Quality Requirements: Dual VSD pumps to supply raw water to ultrafiltration system for turbidity removal. Carbon filtration to remove taste and odour. Potable water disinfection via chlorine dosing.

Daily Treated Water Production: 100.0 KL


Details:

This is the second potable water plant that Dowden's have completed for BMA.

This system was installed and commissioned within 3 weeks to meet BMA's requirements.

The potable water treatment plant uses ultrafiltration technology to treat approximately 100.0 KL / day. The system produces potable water with a quality that exceeds the Australian drinking water guidelines and is used throughout the site.


 